Concrete Footing Cost in 2026: What You'll Pay by Type

Concrete footings cost $5–$15 per linear foot for strip footings and $150–$500 per pier footing. The total cost depends on footing type, depth (driven by frost line), soil conditions, and rebar requirements. This guide covers real pricing for residential and commercial footings.

🧮 Calculate Your Footing

Use our free Footing Calculator for instant concrete volume, rebar quantities, and cost estimates for any footing project.

Concrete Footing Cost by Type

Footing TypeCost (installed)Typical UseTypical Dimensions
Strip / continuous footing$5–$15/linear ftFoundation walls, load-bearing walls16–24" wide × 8–12" deep
Pad / spread footing$75–$300 eachColumn bases, post supports24×24" to 48×48" × 12" deep
Pier / caisson footing$150–$500 eachDecks, porches, deep frost areas10–24" diameter × depth to frost line
Stepped footing$12–$25/linear ftSloped sites, hillside foundationsVaries — steps follow grade
Grade beam$15–$30/linear ftSpans between piers, poor soil12–18" wide × 18–36" deep
Monolithic slab-on-grade$8–$16/sq ft (total slab)Frost-free regions, garagesThickened edge: 12–18" deep at perimeter

Cost Breakdown: Strip Footing (Per 10 Linear Feet)

Here's where the money goes for a typical 20" wide × 10" deep strip footing, 10 feet long:

ComponentCost% of Total
Excavation (trench)$15–$3015–20%
Gravel base (4")$5–$105–8%
Concrete (0.5 yd³)$25–$3520–25%
Rebar (#4, 3 bars continuous)$10–$158–12%
Forms (if needed)$5–$155–10%
Labor (dig, form, pour, strip)$40–$6030–40%
Total per 10 LF$100–$165= $10–$16.50/LF

Frost Line Depth by Region

Footings must extend below the frost line to prevent heaving. This is a code requirement, not a suggestion. Deeper footings = more concrete = higher cost.

RegionFrost DepthExample StatesCost Impact
No frost0–6"FL, HI, Southern CA, TX coastLowest — shallow footings or slab-on-grade
Light frost12–18"GA, SC, NC, AZ, NMModerate — standard depth
Moderate frost24–36"VA, KY, KS, CO, ORHigher — deeper excavation needed
Deep frost36–48"OH, PA, IL, IN, NE, WA (east)High — significant excavation
Severe frost48–72"MN, WI, MI, ND, MT, MEHighest — 4–6 feet deep, may need pier footings

Cost impact: Going from 18" depth to 48" depth roughly doubles the concrete volume and excavation labor. In severe frost areas, pier footings ($150–$500 each) are often more economical than continuous strip footings at 4+ feet deep.

Types of Concrete Footings Explained

Strip / Continuous Footings

The most common type — a continuous strip of concrete that runs under load-bearing walls. Standard for house foundations, garage walls, and any wall that supports structural loads. Width is typically 2× the wall thickness (8" wall = 16" footing minimum).

Pad / Spread Footings

Square or rectangular pads that support individual columns or posts. Common for steel buildings, deck supports, and industrial structures. Sized based on column load and soil bearing capacity — typically 24×24" for light loads up to 48×48" for heavy loads.

Pier / Caisson Footings

Round holes drilled and filled with concrete, often with rebar cages. Used for decks, porches, and in deep frost areas where digging a continuous trench to frost depth would be impractical. Diameter ranges from 10" (fence posts) to 24" (structural).

Stepped Footings

Used on sloped sites where the footing must follow the terrain in steps. Each step must be at least 6" tall and overlap the next section. More labor-intensive (and expensive) than flat footings — budget 2–3× the cost of straight footings.

Footing Sizing Guide

StructureMin. WidthMin. DepthRebar Required
1-story home (wood frame)16"8"#4 × 2 continuous
2-story home20–24"10–12"#4 × 3 continuous
Detached garage16"8"#4 × 2 continuous
Retaining wall (4 ft)24–30"12"#4 × 3 + dowels
Deck pier12–18" diameterTo frost line#4 × 2–4 vertical
Fence post10–12" diameter24–36"None (post is reinforcement)

Important: These are general guidelines based on IRC residential building code for normal soil (2,000+ PSF bearing capacity). Your engineer or local building department may require different sizing based on soil testing and specific loading conditions.

Reinforcement Requirements

Footings need reinforcement to resist cracking from soil movement, loading, and temperature changes:

  • Continuous rebar — #4 bars running the length of strip footings. Minimum 2 bars for 1-story, 3 bars for 2-story.
  • Dowels — Vertical #4 or #5 bars extending up from the footing into the foundation wall. Placed every 24–48" on center. These tie the wall to the footing structurally.
  • Corner bars — L-shaped rebar at corners and intersections. Minimum 24" lap splice length.
  • Pad footing reinforcement — #4 rebar grid in both directions, typically 12" on center.
Rebar ComponentMaterial CostLabor Cost
#4 rebar (continuous)$0.75–$1.25/LF$0.50–$1.00/LF to tie
#5 rebar (heavy loads)$1.00–$1.75/LF$0.75–$1.25/LF to tie
Dowels (#4, 36" long)$2–$4 each$1–$2 each to set

For detailed rebar calculations, use our Rebar Calculator.

DIY vs. Hiring a Contractor

Comparison for a 100-linear-foot strip footing (20" wide × 10" deep):

ItemDIYContractor
Excavation (trencher rental)$200–$400$300–$500
Concrete (~5.5 yd³)$825$825
Rebar$150$200
Forms and gravel$200$200
Labor$0 (your time)$500–$800
Total$1,375–$1,575$2,025–$2,525
Per linear foot$13.75–$15.75$20.25–$25.25

DIY verdict: Savings of ~$650–$950 on 100 LF. DIY footings are feasible for sheds, garages, and additions if you're comfortable with excavation and you have the trench dug before the concrete truck arrives. For home foundations, always hire a pro — inspection requirements alone make DIY impractical.

6 Ways to Reduce Footing Costs

  1. Dig your own trenches. Rent a trencher ($150–$300/day) and excavate yourself. Saves $2–$5/LF.
  2. Use monolithic slab-on-grade where allowed. In frost-free areas, a thickened-edge slab eliminates separate footing costs entirely.
  3. Consider pier footings in deep frost areas. Drilling individual piers is often cheaper than trenching continuous footings 4+ feet deep.
  4. Order concrete in full truck loads. Partial loads incur short-load fees ($50–$100/yd³ under minimum). Plan to pour footings and slabs on the same day when possible.
  5. Get a soil test early. A $300–$500 soil test can confirm good bearing capacity, potentially allowing smaller footings than the default conservative sizing.
  6. Bundle with foundation work. Contractors offer better per-foot pricing when the footing, foundation wall, and slab are all one contract.

Calculate Your Footing Cost

Our free Footing Calculator gives you instant concrete volume, rebar quantities, and cost estimates for strip, pad, and pier footings.

Frequently Asked Questions

How much does a concrete footing cost?

Concrete footings cost $5–$15 per linear foot for strip/continuous footings, $75–$300 per pad footing, and $150–$500 per pier footing. A full foundation perimeter footing (150 linear feet for a typical home) costs $2,500–$5,000 for the footing alone, not including the foundation walls above.

How much does a concrete footing cost per square foot?

When measured per square foot of footing surface, concrete footings cost $5–$12/sq ft for materials and labor. However, footings are more commonly priced per linear foot ($5–$15/LF) or per cubic yard of concrete ($150–$200/yd³ installed) since their width is determined by engineering, not customer preference.

How deep do concrete footings need to be?

Footings must extend below the frost line, which varies by location: 12" in the deep South, 36" in the upper Midwest, and 48"+ in northern states like Minnesota and Montana. Check your local building code for exact depth. Below-frost-line depth prevents heaving and cracking.

What is the difference between a footing and a foundation?

The footing is the widened base that spreads the building load across the soil. The foundation wall sits on top of the footing and extends up to grade level. Think of the footing as the 'shoe' and the foundation as the 'leg.' Both are required for most structures; footings are always poured first.

Can I pour my own concrete footings?

For non-structural applications (shed, fence posts, deck posts), DIY is feasible. For home foundations and structural footings, hire a licensed contractor — footings require proper sizing based on soil bearing capacity, correct rebar placement, and inspections. Mistakes are buried underground and extremely expensive to fix.

How long do concrete footings take to cure before building on them?

Concrete footings reach sufficient strength for foundation wall construction in 2–3 days (reaching about 50% of design strength). Full cure takes 28 days. Most contractors pour foundation walls 2–7 days after footing placement. In cold weather, curing takes longer and may require insulated blankets.

Related Guides